Battery storage commissioning checklist

A commissioning checklist for battery energy storage: what's installed, the inspection, BS 7671 test references, system function tests and grid tests, signed off per system.

Free 7-day trial · no credit card required

6
Sections
23
Fields
11
Field types

What should a battery storage commissioning checklist include?

It should cover the system details and class, an inspection of equipment, protection, location and labelling, references to the BS 7671 tests (with fault current checked in every operating mode), function tests of controls, alarms, charge-discharge, thermal, ventilation and fire systems, and grid tests: loss of mains, export limitation and back-up changeover.

Last updated . Facts checked on 30 September 2026 against MCS: MIS 3012 Issue 1.0, The Battery Standard.

Who uses it

The commissioning engineer on a commercial battery or solar-plus-storage job, one record per storage system.

When

After installation and before handover, and again when a battery system is extended or its controls are changed.

In Integrio

Build it once in the Form Builder (Office User), attach it to projects, and your team fills it in on iOS or Android, offline if needed.

IntegrioFree template · integrio.app/forms/battery-storage-commissioning-checklist/

Battery storage commissioning checklist

A commissioning checklist for battery energy storage: what's installed, the inspection, BS 7671 test references, system function tests and grid tests, signed off per system.

Project
Site
Completed by
Date

The template

What's in the battery storage commissioning checklist?

6 sections and 23 fields. Copy them into any format, print this page, or set the form up in Integrio.

  1. 1.System details

    1. 1.1

      Installation addressRequired

      Text
    2. 1.2

      Commissioning dateRequired

      Date
    3. 1.3

      Battery make, model and serial numbersRequired

      Notes
    4. 1.4

      Inverter / PCE make, model and serial numbersRequired

      Notes
    5. 1.5

      System classRequired

      Classes as defined in MCS MIS 3012.

      • Class 1: all-in-one packaged system
      • Class 2: separate PCE and battery, one manufacturer
      • Class 3: PCE and battery from different manufacturers
      • Class 4: bespoke, installer responsible for integration
      Choose one
    6. 1.6

      Maximum power outputRequired(kW)

      Reading
    7. 1.7

      Usable capacityRequired(kWh)

      Reading
    8. 1.8

      Back-up or island modeRequired

      • Yes
      • No
      Yes / No
    9. 1.9

      Test instruments and serial numbersRequired

      Text
  2. 2.Inspection

    1. 2.1

      Equipment and protectionRequired

      CheckPassFailN/A
      Installed to the design and manufacturer's instructions○○○
      Equipment undamaged○○○
      Conductors connected, identified and routed correctly○○○
      Switchgear rated for the DC and AC voltage and current○○○
      Earthing and bonding in place○○○
      RCD protection where required○○○
      Dual supply and other warning labels fixed and durable○○○
      Checklist grid
    2. 2.2

      LocationRequired

      CheckPassFailN/A
      Ventilation suits the battery and PCE○○○
      Clearances meet the manufacturer's specification○○○
      IP rating suits the location○○○
      Protected from impact damage○○○
      Above foreseeable flood level○○○
      Fire detection fitted where the room is rarely visited○○○
      Access kept clear for maintenance○○○
      Checklist grid
  3. 3.Back-up and island mode

    Only for systems that supply the site when the grid is off.

    1. 3.1

      Island mode arrangement

      ↳ Shown when Back-up or island mode is Yes

      CheckPassFailN/A
      Grid conductors isolated in island mode○○○
      Consumer's earth electrode provided○○○
      RCDs give the disconnection times needed in island mode○○○
      Surge protection fitted○○○
      Load shedding or staggered start on changeover○○○
      Checklist grid
    2. 3.2

      Earth electrode resistance(Ω)

      ↳ Shown when Back-up or island mode is Yes

      Reading
  4. 4.Electrical tests

    1. 4.1

      BS 7671 certificate and schedule referenceRequired

      Text
    2. 4.2

      Fault current and loop impedance verified in every operating modeRequired

      Charging-mode tests with all inverters and bi-directional converters disconnected.

      • Yes
      • No
      Yes / No
    3. 4.3

      Highest prospective fault currentRequired(kA)

      Reading
  5. 5.System and grid tests

    1. 5.1

      Function testsRequired

      CheckPassFailN/A
      Controls and data logging working○○○
      Monitoring connected and reporting○○○
      Displays and alarms○○○
      Charges and discharges correctly○○○
      Thermal management○○○
      Ventilation system and controls○○○
      Fire detection or suppression interface○○○
      Loss of mains (G98 / G99)○○○
      Export limitation (G100)○○○
      Back-up changeover and power quality○○○
      Checklist grid
    2. 5.2

      Manufacturer's commissioning report

      Attach, or give its reference.

      File upload
    3. 5.3

      DNO witnessed the grid tests

      • Yes
      • No
      Yes / No
  6. 6.Result and sign-off

    1. 6.1

      Overall resultRequired

      • Pass
      • Fail
      Pass / Fail
    2. 6.2

      Defects and actionsRequired

      ↳ Shown when Overall result is Fail

      Notes
    3. 6.3

      Photo of the installed system and labelsRequired

      Photo
    4. 6.4

      Commissioned by (signature)Required

      Signature

Battery storage commissioning checklist from Integrio, free to use and adapt. Run it on phones, offline, with photos and signatures: integrio.app · Free 7-day trial, no credit card required.

From the field

How do you get the most from a battery storage commissioning checklist?

01

Test fault current in every mode

A battery changes the fault current and loop impedance depending on whether it's charging, discharging or islanded. One set of readings taken with everything running isn't enough.

02

Record the class before you start

An all-in-one packaged unit and a bespoke system with parts from three manufacturers need different amounts of checking. Setting the class first tells the engineer how deep to go.

03

Prove changeover under load

If the system provides back-up, pull the supply with the essential loads running and watch what switches, what sheds and how long it takes. That's the moment the customer will one day rely on.

04

Keep the manufacturer's report with yours

Most battery makers have their own commissioning app or report. Attach it to the same record so warranty claims have the serials, settings and your test results together.

Frequently asked questions

What do people ask about the battery storage commissioning checklist?

Ask our team →

What does MCS require when commissioning a battery?

+

MIS 3012 says the storage system is commissioned to a documented procedure and gives a model checklist based on Section 12 of the IET Code of Practice, used in addition to BS 7671 certification. Earth fault loop impedance and prospective fault current must be verified for all operating modes.

Source: MCS: MIS 3012 Issue 1.0, The Battery Standard

Does MIS 3012 cover commercial battery systems?

+

MIS 3012 covers storage systems for permanent buildings up to 50 kW, connected behind the supply meter. In-front-of-meter, off-grid and UPS systems are out of its scope. The IET Code of Practice for Electrical Energy Storage Systems covers dwellings, commercial and industrial installations.

Sources: MCS: MIS 3012 Issue 1.0, The Battery Standard, IET: Code of Practice for Electrical Energy Storage Systems, 3rd Edition

Does PAS 63100 apply to commercial battery storage?

+

PAS 63100:2024 sets fire safety requirements for small-scale storage systems in domestic dwellings. MCS notes the 3rd Edition IET Code of Practice says it should be considered. For a commercial site, work to the Code of Practice and the manufacturer's instructions, and record the fire safety checks on this form.

Source: MCS: Update on PAS 63100 and IET Code of Practice 3rd Edition

Is this battery storage commissioning checklist free?

+

Yes. Use the questions in your own format, or set them up in Integrio as a testing form on each battery system.

How do I use this template in Integrio?

+

Build it once in the Integrio Form Builder, which is on the Office User plan (£65 per user per month), and attach it to the battery product so each system gets the same record with its serials. Engineers fill it in on the mobile app on the Field Service User plan (£15 per user per month), offline if needed.

Stop retyping paper forms

Run the battery storage commissioning checklist on your team's phones.