G99 application checklist for solar PV and battery installers

A checklist for installers preparing a G99 grid-connection application: which route applies, what to gather, what to attach, and each DNO step through to commissioning confirmation.

Free 7-day trial · no credit card required

5
Sections
33
Fields
10
Field types

What do you need for a G99 application?

For a G99 application you need the customer and site details, the total AC rating of all generation and storage per phase, existing MPANs and connection agreements, a single line diagram, equipment details with type test references, import and export requirements, and a target commissioning date. Forms go to the local DNO, not to ENA.

Last updated . Facts checked on 30 September 2026 against ENA: Connecting commercial generation to the electricity networks and ENA: Connection of Power Generating Modules to DNO Distribution Networks in accordance with EREC G99 (v9, October 2022).

Who uses it

Installers' project managers and design engineers preparing the grid-connection paperwork for a commercial PV or battery job.

When

At design stage, before the application goes to the DNO, then kept open until the DNO has confirmed commissioning.

In Integrio

Build it once in the Form Builder (Office User), attach it to projects, and your team fills it in on iOS or Android, offline if needed.

IntegrioFree template · integrio.app/forms/g99-application-checklist/

G99 application checklist for solar PV and battery installers

A checklist for installers preparing a G99 grid-connection application: which route applies, what to gather, what to attach, and each DNO step through to commissioning confirmation.

Project
Site
Completed by
Date

The template

What's in the g99 application checklist?

5 sections and 33 fields. Copy them into any format, print this page, or set the form up in Integrio.

  1. 1.G98 or G99?

    Add up every inverter on the site, including batteries, before choosing the route.

    1. 1.1

      Project and siteRequired

      Text
    2. 1.2

      TechnologyRequired

      • Solar PV
      • Battery storage
      • Other generation
      Choose any
    3. 1.3

      SupplyRequired

      • Single phase
      • Three phase
      Choose one
    4. 1.4

      Total AC rating of all generation and storageRequired(A per phase)

      Aggregate, including existing generation. Above 16 A per phase, G99 applies.

      Reading
    5. 1.5

      Connection routeRequired

      • G98: install, then notify the DNO
      • G99 fast track (Form A1-2)
      • G99 up to 17 kW single phase / 50 kW three phase (Form A1-1)
      • G99 standard application form
      Choose one
    6. 1.6

      Export limitation scheme (G100) needed?Required

      • Yes
      • No
      Yes / No
  2. 2.Site and customer information

    Mostly Part 1 of the G99 standard application form. Get it from the customer early.

    1. 2.1

      Customer (the Generator) name and contactRequired

      The customer is the Generator on the form, even for a battery-only site.

      Text
    2. 2.2

      Site boundary plan (1:500) or postal addressRequired

      File upload
    3. 2.3

      Existing import MPANRequired

      Text
    4. 2.4

      Existing export MPAN

      Leave blank if there is no export meter yet.

      Text
    5. 2.5

      Existing connection agreements or generation on site

      Notes
    6. 2.6

      Target commissioning dateRequired

      Date
  3. 3.Equipment and attachments

    1. 3.1

      Inverter / PCE make, model and quantityRequired

      Notes
    2. 3.2

      Type test reference numbersRequired

      From the ENA register or the manufacturer's verification report.

      Text
    3. 3.3

      Battery make, model and usable capacity

      ↳ Shown when Technology includes Battery storage

      Text
    4. 3.4

      Interface protectionRequired

      • Integral to type-tested inverters
      • Separate G99 protection relay
      Choose one
    5. 3.5

      Single line diagramRequired

      File upload
    6. 3.6

      Datasheets and type test certificatesRequired

      File upload
    7. 3.7

      G100 export limitation details

      ↳ Shown when Export limitation scheme is Yes

      File upload
  4. 4.DNO submission and offer

    1. 4.1

      DNORequired

      • National Grid Electricity Distribution
      • UK Power Networks
      • Northern Powergrid
      • Electricity North West
      • SP Energy Networks
      • Scottish and Southern Electricity Networks
      • Northern Ireland Electricity Networks
      • Independent DNO (IDNO)
      Dropdown
    2. 4.2

      Submitted via

      • ENA Connect Direct
      • DNO portal
      • Email
      Choose one
    3. 4.3

      Date submittedRequired

      Date
    4. 4.4

      DNO referenceRequired

      Text
    5. 4.5

      Quote type requested

      ↳ Shown when Connection route is G99 standard application form

      • Budget estimate
      • Formal quote
      Choose one
    6. 4.6

      Connection offer received and accepted?

      • Yes
      • No
      Yes / No
    7. 4.7

      Conditions in the offer

      Export limit, reinforcement works, dates, extra data (Part 4 or 5) requested.

      ↳ Shown when Connection offer received and accepted is Yes

      Notes
  5. 5.Commissioning and DNO confirmation

    1. 5.1

      Will the DNO witness the tests?Required

      • Yes
      • No
      • Not confirmed yet
      Choose one
    2. 5.2

      Witness test date

      ↳ Shown when Will the DNO witness the tests is Yes

      Date
    3. 5.3

      Commissioning dateRequired

      Date
    4. 5.4

      Commissioning test recordsRequired

      Attach the PV and battery commissioning sheets.

      File upload
    5. 5.5

      Date commissioning confirmation sent to the DNORequired

      Fast track and G98: within 28 days of commissioning.

      Date
    6. 5.6

      Final Operational Notification received

      Types B, C and D (1 MW and above) cannot run in parallel without it.

      • Yes
      • No
      Yes / No
    7. 5.7

      Checked byRequired

      Signature

G99 application checklist from Integrio, free to use and adapt. Run it on phones, offline, with photos and signatures: integrio.app · Free 7-day trial, no credit card required.

From the field

How do you get the most from a g99 application checklist?

01

Count the battery as generation

A battery inverter adds to the per-phase total just like a PV inverter. Adding storage to an existing G98 site is the classic way to end up needing G99 without noticing.

02

Chase the MPANs on day one

The import MPAN, any export MPAN and details of existing connection agreements come from the customer, and they are the items most often still missing when the drawings are finished.

03

Put type test references on the form

Where inverters or protection are type tested, quoting the reference numbers lets the DNO check compliance without asking for it at site. Keep the certificates with the job.

04

Book commissioning inside the window

On fast track, the planned commissioning date has to sit between 10 working days and three months after you apply. Schedule the crew and the pallet deliveries to that date, not the other way round.

Frequently asked questions

What do people ask about the g99 application checklist?

Ask our team →

When does G98 apply instead of G99?

+

ENA says G98 applies to generation under 3.68 kW per phase (16 A) and G99 above it. MIS 3002 makes clear the threshold is the aggregate AC output of all generators on the supply, so a 3 kW PV system plus a 3 kW battery on one single-phase supply needs G99. Under G98 you install first and notify the DNO within 28 days.

Sources: ENA: Connecting commercial generation to the electricity networks, MCS: MIS 3002 Issue 6.0, The Solar PV Installation Standard (18/03/2026), Electricity North West: EREC G98 & EREC G99 frequently asked questions

What is the G99 fast-track process?

+

Since 9 November 2022, small single installations whose aggregate capacity, storage included, stays within 32 A or 60 A per phase (depending on the procedure), all on fully type-tested inverters that won't run on loss of mains, can apply on Form A1-2. Commissioning must be planned 10 working days to three months after applying, and confirmed on Form A3-2 within 28 days.

Source: ENA: Connecting commercial generation to the electricity networks

Will the DNO witness my commissioning tests?

+

Sometimes. The installer carries out the tests, and the DNO may choose to witness them, for a fee. Which tests are witnessed depends on what type tests, manufacturer data and studies have already proved. Type-tested interface protection can remove the need, although on-site function tests are still needed if the protection was type tested on its own.

Sources: National Grid Electricity Distribution: G99 connection procedures, Electricity North West: EREC G98 & EREC G99 frequently asked questions

Can Integrio submit the G99 application for me?

+

No. Integrio does not submit G98 or G99 applications or talk to DNOs. Applications go to your local DNO, directly or through ENA Connect Direct, which is free for installers. Integrio holds this checklist, the attachments and the dates against the project, and a workflow can start the next task when a step is done.

Source: ENA: ENA Connect Direct

Is this G99 application checklist free?

+

Yes. Copy the fields into your own checklist or spreadsheet, or set it up in Integrio so every commercial PV and battery job follows the same steps.

How do I use this template in Integrio?

+

Build it in the Integrio Form Builder, which is on the Office User plan (£65 per user per month), and attach it to the project so each job follows the same steps. Anyone on the Field Service User plan (£15 per user per month) can fill it in on the mobile app, offline if needed, with file uploads and signatures.