EV charger commissioning checklist template

A per-charger install and commissioning record for workplace, fleet and multi-site charge point rollouts: where it is, what it is, how it's supplied and protected, what it measured, and who accepted it.

Free 7-day trial · no credit card required

5
Sections
36
Fields
12
Field types

What should an EV charger commissioning checklist include?

An EV charger commissioning checklist should record, for each charge point: the site and bay, make, model, serial and rating; the supply circuit and protective devices; the earthing arrangement and any PME measure; test readings with units; RCD and DC fault protection; a test charge; connectivity and smart settings; handover to the customer; and signatures.

Last updated . Facts checked on 30 September 2026 against IET: Code of Practice for Electric Vehicle Charging Equipment Installation, 5th edition and IET Wiring Matters: BS 7671:2018+A1 changes, including section 722.

Who uses it

Electricians and commissioning engineers installing commercial, workplace, fleet or car park charge points, one record per charger.

When

As each charge point is installed and tested, before it is energised for customer use, and again if a unit is replaced.

In Integrio

Build it once in the Form Builder (Office User), attach it to projects, and your team fills it in on iOS or Android, offline if needed.

IntegrioFree template · integrio.app/forms/ev-charger-commissioning-checklist/

EV charger commissioning checklist template

A per-charger install and commissioning record for workplace, fleet and multi-site charge point rollouts: where it is, what it is, how it's supplied and protected, what it measured, and who accepted it.

Project
Site
Completed by
Date

The template

What's in the ev charger commissioning checklist?

5 sections and 36 fields. Copy them into any format, print this page, or set the form up in Integrio.

  1. 1.Charge point and location

    Enough detail to find this exact unit on a site with forty of them.

    1. 1.1

      Project and siteRequired

      Text
    2. 1.2

      Charge point ID or bay numberRequired

      Use the same ID as the bay marking and the operator's back office.

      Text
    3. 1.3

      Location typeRequired

      • Surface car park
      • Multi-storey or undercroft
      • Fleet or bus depot
      • Loading bay or yard
      • Kerbside
      • Other
      Dropdown
    4. 1.4

      Intended useRequired

      • Workplace or staff
      • Fleet
      • Visitors or customers
      • Public
      Choose one
    5. 1.5

      Make and modelRequired

      Text
    6. 1.6

      Serial numberRequired

      Photograph the rating plate as well.

      Text
    7. 1.7

      Rated outputRequired(kW)

      Reading
    8. 1.8

      ConnectorRequired

      • Type 2 socket (untethered)
      • Type 2 tethered
      • CCS
      • CHAdeMO
      • Other
      Choose one
    9. 1.9

      Photo of the installed unit and bayRequired

      Photo
  2. 2.Supply, protection and earthing

    1. 2.1

      Supplied from (board and circuit)Required

      e.g. DB-EV2, way 5 L1–L3.

      Text
    2. 2.2

      SupplyRequired

      • Single-phase
      • Three-phase
      Choose one
    3. 2.3

      Cable sizeRequired(mm²)

      Reading
    4. 2.4

      Overcurrent device ratingRequired(A)

      Reading
    5. 2.5

      RCD and DC fault protectionRequired

      • RCD Type B
      • RCD Type A with RDC-DD (6 mA DC)
      • RCD Type F with RDC-DD (6 mA DC)
      • Built into the charger (per manufacturer)
      Choose one
    6. 2.6

      Earthing arrangementRequired

      • TN-C-S (PME)
      • TN-S
      • TT
      Choose one
    7. 2.7

      PME measure for an outdoor charge point

      Record which option of BS 7671 regulation 722.411.4.1 the design uses.

      ↳ Shown when Earthing arrangement is TN-C-S (PME)

      • Three-phase with balanced loads
      • Earth electrode
      • Open PEN detection built into the charger
      • Separate open PEN device
      • Not outdoors, not needed
      Choose one
    8. 2.8

      Earth electrode resistance(Ω)

      ↳ Shown when Earthing arrangement is TT, or PME measure is Earth electrode

      Reading
  3. 3.Test readings

    Record the reading and its unit, not just a tick.

    1. 3.1

      Continuity of protective conductors (R1 + R2)Required(Ω)

      Reading
    2. 3.2

      Insulation resistanceRequired(MΩ)

      Reading
    3. 3.3

      Earth fault loop impedance (Zs)Required(Ω)

      Reading
    4. 3.4

      Prospective fault currentRequired(kA)

      Reading
    5. 3.5

      RCD trip time at rated residual currentRequired(ms)

      Reading
    6. 3.6

      Polarity and phase rotationRequired

      • Pass
      • Fail
      Pass / Fail
    7. 3.7

      Test instrument and serialRequired

      Text
    8. 3.8

      Electrical certificate reference

      The certificate itself is issued under your own scheme.

      Text
  4. 4.Charger, connectivity and smart checks

    1. 4.1

      Functional checksRequired

      CheckPassFailN/A
      Powers up with no fault codes○○○
      Test charge with vehicle or EV simulator○○○
      Starts and stops by app, RFID or plug-in as set up○○○
      Current limit or load management set to design○○○
      Connected to the network (4G, Wi-Fi or Ethernet)○○○
      Showing online in the operator's back office○○○
      Firmware updated to the version agreed○○○
      Checklist grid
    2. 4.2

      Do the Smart Charge Points Regulations apply to this unit?Required

      • Yes: private or workplace, under 50 kW
      • No: public charge point
      • No: rapid (50 kW or more)
      • Not sure: check with the supplier
      Choose one
    3. 4.3

      Seller's statement of compliance received

      ↳ Shown when the Regulations apply

      • Yes
      • No
      Yes / No
    4. 4.4

      Default off-peak charging hours shown to the owner

      The owner can accept, remove or change them.

      ↳ Shown when the Regulations apply

      • Yes
      • No
      Yes / No
    5. 4.5

      Fault details and action

      ↳ Shown when any functional check is Fail

      Notes
  5. 5.Handover and sign-off

    1. 5.1

      Handed over

      • User instructions
      • RFID cards
      • Back office access
      • Bay signage and markings in place
      • Warranty details
      Choose any
    2. 5.2

      Ready for useRequired

      • Yes
      • No
      Yes / No
    3. 5.3

      What's outstanding

      ↳ Shown when Ready for use is No

      Notes
    4. 5.4

      Installer name and signatureRequired

      Signature
    5. 5.5

      Customer name and signatureRequired

      Signature
    6. 5.6

      Date commissionedRequired

      Date

EV charger commissioning checklist from Integrio, free to use and adapt. Run it on phones, offline, with photos and signatures: integrio.app · Free 7-day trial, no credit card required.

From the field

How do you get the most from a ev charger commissioning checklist?

01

Use one ID everywhere

The bay marking, the back office and this form should share one charge point ID. Otherwise a fault reported on bay 12 gets investigated on the wrong charger.

02

Photograph the rating plate before the cover goes on

Serials and part numbers are hard to read once a unit is mounted and sealed, and you'll need them for every warranty claim.

03

Record the PME decision per charger

On a mixed site some units are indoors and some aren't. Note which earthing measure each unit relies on, so a later visit doesn't have to work it out again.

04

Prove it charges, not just that it's online

A charger can show online and still refuse a vehicle. Finish every record with a real test charge or a simulator test.

Frequently asked questions

What do people ask about the ev charger commissioning checklist?

Ask our team →

Is this EV charger commissioning checklist free?

+

Yes. Use the fields on this page however suits you: print them, put them in a spreadsheet, or build them into Integrio so every charger on every site is recorded the same way.

What does BS 7671 say about PME supplies to EV chargers?

+

Section 722 does not allow a PME supply to a charge point located outdoors, or one that may charge a vehicle outdoors, unless one of the options in regulation 722.411.4.1 is met: a balanced three-phase installation, an earth electrode, a device that detects a PEN fault, or an equivalent device. Check the current edition of BS 7671 and the IET Code of Practice for the full wording.

Sources: IET Wiring Matters: BS 7671:2018+A1 changes, including section 722, IET: Code of Practice for Electric Vehicle Charging Equipment Installation, 5th edition

Do the Smart Charge Points Regulations apply to commercial chargers?

+

They apply to charge points sold in Great Britain for cars and vans, but not to public charge points or rapid charge points of 50 kW or more. Workplace charge points are not treated as public, so they can be in scope. In-scope units need smart functionality, default off-peak charging hours and a randomised delay, and the seller supplies a statement of compliance.

Sources: Smart Charge Points Regulations 2021, regulation 3 (application), The Electric Vehicles (Smart Charge Points) Regulations 2021

Is Integrio a charge point management system?

+

No. Integrio records the install, the product data and the commissioning for each charger, and supports aftercare with tickets and maintenance visits. Charging sessions, tariffs and OCPP connections stay in your charge point management system.

How do I use this template in Integrio?

+

Build it once in the Integrio Form Builder, which is on the Office User plan (£65 per user per month), and attach it to the charger product so every unit gets the same testing form. Engineers fill it in on the mobile app on the Field Service User plan (£15 per user per month), offline if the car park has no signal.

Stop retyping paper forms

Run the ev charger commissioning checklist on your team's phones.